The installation has commenced at Hello Fresh Warehouse, Nuneaton. The Aspiration Fire Detection System is now fully second fixed and is made up of over 3000m of aspiration pipework. Our engineers have completed 80% of the office areas, including the ground floor changing area. We are hoping to have the job fully installed by the end of November, with final commissioning and testing to be undertaken and completed by the middle of December, in line with the main contractor’s programme of works.