Block B has been successfully handed over with block A due to be commissioned by mid-March. The original completion date of November 20 was pushed back due to site closure on various occasions and delays with labor for the main contractor due to the Covid-19 pandemic. Despite these initial setbacks, we are still on track for practical completion for the new handover date of March 21.